PROJECT
MOMAX
@
T.S.T - MTR
Location : T.S.T MTR Pop-up Store
Year : 2025
Size : 150 sqft
Team : Ronald Mau, Willis Lee, Lucy Youn, Ning Ting, Jophy Fung
![]() | ![]() | ![]() |
|---|---|---|
![]() | ![]() | ![]() |
![]() | ![]() | ![]() |
![]() | ![]() | ![]() |
MOMAX Pop-Up Store @ Tsim Sha Tsui MTR Station
Location: Tsim Sha Tsui MTR Station, Hong Kong
Size: Approx. 150 sqft
Project Duration: ~3 months (including application, approval, construction, and inspection)
Completion Year: 2025
Scope of Work: Furniture installation, signage replacement, lighting enhancement, surface finishes
Project Overview
This project marks ENOCHDECO’s first retail store within an MTR station, a highly regulated environment where safety, material compliance, and precision in execution are of paramount importance. Despite the store’s compact size of only 150 sqft, the time and effort required exceeded that of many larger projects.
The MTR Corporation enforces strict safety and construction requirements due to the station’s high passenger traffic. All materials must come from their pre-approved list, supported by multiple certifications and test reports. The documentation and submission process alone took nearly two months before construction could begin.
Project Timeline
Site Handover: June 2025
Construction Start: May-August 2025
Fit-Out Duration: 3–4 weeks
Inspection & Approval: Additional 2 weeks after completion
Given the constraints, we retained the existing air-conditioning and fire services systems, focusing instead on new furniture, branded decals, signage updates, and enhanced lighting. Even with a minimalist scope, the rigorous approval process and site conditions extended the overall timeline to approximately three months.
Acknowledgements
We would like to express our sincere gratitude to the MOMAX team for their dedication and patience, which were instrumental in bringing this project to life. Throughout the process, their collaboration was exemplary.
Special thanks go to our design lead, Jophy Fung, whose meticulous coordination and dedication earned high praise from both the client and the MTR team. His attention to detail and hands-on approach ensured every aspect met the highest standards. We look forward to working with him on many more projects in the future.
We also extend our sincere thanks to the MTR design team. While their standards are exceptionally high and their processes rigorous, we found their approach to be positive and constructive. Their guidance and support played a crucial role in ensuring the project’s smooth completion. We truly value this experience and look forward to future opportunities to collaborate with MTR again.